Yihua has completed pre-delivery testing of DAF wastewater treatment equipment prepared for an industrial project in Estonia. The verification process focused on equipment completeness, operational readiness, control response, documentation, and transport preparation before international shipment.
Pre-delivery testing creates a practical handover point between manufacturing and site installation. It helps confirm that the supplied components match the approved equipment scope and allows potential assembly or interface issues to be corrected before the system reaches the project site.
The first stage reviewed the DAF tank, recycle system, skimming assembly, pumps, valves, instruments, piping interfaces, sludge discharge points, and electrical components included in the delivery scope. Equipment identification and connection points were checked to support accurate installation in Estonia.
The inspection also considered access for operation and maintenance. Skimmer service space, instrument visibility, valve access, and cleaning points influence how efficiently the DAF wastewater treatment equipment can be operated after commissioning.
The mechanical and electrical components were operated through their available test sequences. The skimming mechanism was checked for correct direction, smooth movement, and stable alignment. Pumps and actuated components were reviewed for abnormal noise, vibration, or leakage.
The control panel was tested to verify start and stop commands, operating status, alarms, emergency functions, and relevant protective logic. Each connected load was checked individually before the overall sequence was reviewed.
A clean water circulation test was used to examine the hydraulic path through the equipment. Valves, pressure points, recycle piping, and discharge connections were observed during operation. This test helps identify installation defects and leakage before packing, but it does not establish treatment efficiency for the actual wastewater.
![]()
DAF performance depends on more than mechanical operation. The Estonia project team will still need to optimize chemical conditioning, recycle flow, dissolved air settings, hydraulic loading, skimming frequency, and sludge discharge using representative wastewater.
Influent oil, TSS, temperature, pH, surfactants, and floc characteristics can all affect flotation. Site commissioning should therefore compare operating conditions with the design basis and adjust the system according to observed floc formation and clarified water quality.
Before packing, the equipment scope should be reconciled with the packing list and technical documents. Installation drawings, interface information, operating guidance, component records, and available test documentation support a more organized site handover.
Residual test water is drained from tanks, pumps, and piping. Open connections are sealed, instruments are protected, and movable components are secured. These measures are especially important for delivery to a cold climate because trapped water can freeze during transport or temporary storage.
The completed pre-delivery testing confirms that the Yihua DAF wastewater treatment equipment has passed its planned factory checks before shipment to Estonia. The process reduces avoidable installation uncertainty and supports a more efficient site handover. Final treatment performance will be established during commissioning with actual wastewater, correct chemical dosing, suitable operating settings, and trained plant personnel.